The North Carolina men’s and women’s soccer teams will not be playing at the new Fetzer Field when their seasons start in September.
The Fetzer Field project, which began in May 2017, is one of three projects that was expected to be done this August, along with an indoor football practice facility and a new field hockey stadium at Ehringhaus Field.
However, Mike Bunting, the UNC associate athletic director for facility planning and management, said the soccer field project will no longer finish on time.
"The original schedule is that both projects would be complete by early August of this year," Bunting said when referring to the Fetzer Field and football facility projects. "Our schedule for both projects has slipped some."
The field hockey stadium is still set to be completed in August, according to UNC athletic director Bubba Cunningham, but the other two projects will not be done on that same timeline.
“We now anticipate that the indoor (football) practice facility will be complete in September and the soccer/lacrosse stadium will be complete in November,” Bunting said.
Football construction is at a delay, putting pressure on the program. If the indoor practice facility is not substantially completed by Sept. 1, 2018, head football coach Larry Fedora has an option to terminate his contract without cause or having to pay liquidated damages to the school. When reached for comment, Cunningham stated the project would be substantially done by that time.
The cost of the football practice facility and the renovation of Fetzer field was raised 22 percent as of July of 2017, according to the News and Observer. The price was initially expected to be $55 million, but rose to more than $67 million.
For the men’s and women’s soccer teams, it marks the second consecutive year where the teams are displaced from their permanent home.