Dana Leeson, associate director of construction management, said workers in the quad lost about five days of work during the storm.
“The contractor couldn’t come into work same as the workers and same as the students,” he said. “The icy conditions on the roads were dangerous for people to come in.”
Workers have been removing asbestos from the insulation in the steam lines since June. The project is supposed to finish in March.
The process involves shutting off steam lines to work on them.
“We were delayed a bit, but it wasn’t just because of the icy roads,” he said. “We couldn’t shut down a couple of the lines to make sure everyone had steam and heat.”
Because a full work week was lost, the project may stretch into the first or even second week of April. But Leeson said most of the barriers will be cleared by the end of March.
“There’s a lot of work going on above ground, but most of the work is being done below ground that people can’t see,” he said.
Leeson said the project is still within its $5 million budget.